Step 1: Place the first 2 cans or vessel sections on fit up bed, and rotate one can so that the seam is at 180 degrees from the seam of the other section.

 

Step 2: Move the fit up carriage to match the cans using the elevation, side/side shift and track drive features. The fit up is done with a single operator using a pendant remote control.

 

Step 3: The fit up rolls are then used to adjust the gap between the cans. Once the gap is closed and the gaps are fully aligned, then the weld can be tacked.

 

Step 4: Continue additional fit up around the full circumference of the cans, and place tack welds as required

 

Step 5: If making use of Wind Tower Welding Line, move into place and complete the internal ID weld

 

Step 6: After the inside root pass is complete, the manipulator is then repositioned to do the outside circumference of the cans, typically utilizing the submerged arc process.

 

Step 7: Next, repeat the fit up and the manipulator welds as previously completed. You can then grow the line until it has reached its maximum length. Cans. http://www.weldc.com/

 